Knife River Corporation has provided an update on the reconstruction of East Century Avenue. The temporary gravel roadway will remain until mid-August. Travelers are reminded to follow traffic control signage and stay alert in the work zone.
The majority of watermain installation is complete, and crews are now focusing on the new storm sewer near Roosevelt Drive, progressing eastward steadily.
All underground utility work from the western project limit to just past Stonewall Drive is finished. Base rock has been placed up to Patriot Drive, with concrete operations set to begin soon.
For inquiries or concerns about the project, residents can contact Andrew Osborn via email or at 701-989-4959.
Andrew Osborn expressed appreciation for residents' understanding during this period, stating that these improvements aim to enhance safety and efficiency in the community's transportation network.