Knife River updates on East Century Avenue reconstruction progress

Webp 5d3p6n8jooet8j1efxas8m172v54

Michael Schmitz Mayor | Bismarck ND City Government

Michael Schmitz Mayor | Bismarck ND City Government

Residents have been informed about the ongoing reconstruction of East Century Avenue by Knife River Corporation. The temporary gravel roadway will remain until mid-August, and travelers are urged to follow traffic control signage in the work zone.

The majority of watermain installation is complete, with crews now focusing on the new storm sewer near Roosevelt Drive. This work is moving eastward steadily.

All underground utility work from the western project limit to just past Stonewall Drive is finished. Base rock has been placed up to Patriot Drive, and concrete operations will commence soon.

For inquiries or concerns, residents can contact Andrew Osborn via email or phone at 701-989-4959.

Andrew Osborn stated: "We understand that road construction can be disruptive to your daily routine, we appreciate your understanding and cooperation during this period of improvement." The goal is to create a safer and more efficient transportation network for the community.

Sincerely,

Andrew Osborn

Public Relations Coordinator Knife River Corporation

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS